Macarthur Mazda

Macarthur Mazda, called on the experience and expertise of Petrolink Engineering to install a tank and fuel delivery facility at its brand-new state-of-the-art showroom and service centre in Campbelltown, on Sydney’s south western outskirts in 2017.

Project Spotlight

  • Client
  • Macarthur Mazda
  • Project Name
  • Fuel Tank Installation
  • Project Location
  • Campbelltown, NSW
  • Contracts Value
  • $290,000
  • Project Timeframe
  • 2 Months

The installation of a triple compartment 45,000 litre tank and bowsers to was engineered to dispense two petrol options and diesel. The engineers and technicians faced significant challenges with most of the new complex already constructed and the access to the site being tight and limited.

In addition to planning the installation, the Petrolink team also liaised with council and local authorities to ensure a smooth DA process so works could commence on time.

Petrolink’s technicians and project managers commenced with the removal of already laid concrete slabs and stormwater services. Security & safety fencing was essential as the dealership was already taking on new cars and the trades involved in the building works were scurrying for a deadline.

The commencement of excavation in preparation for the large tank to be delivered and installed involved a 50-ton crane to be brought in to lift the 10 metre long tank over fencing and barriers to be lowered into the excavated site. This exercise posed a range of challenges such as crowd control, dealing with overhead power lines, weight limitations and very tight clearances.

A pre-requisite from Macarthur Mazda was that the installation did not overly affect the day-to-day operation of the high-profiled dealership.

mazda-2
The project was brought in on time and to budget, despite weather stoppages and site limitations and installed to the strict EPA & local government conditions and to Australian Standards.

Project specifications included:

  • Source and supply HDPE 45,000 lite tank
  • Supply and infrastructure of X bowsers
  • Council negotiation and DA sign-off
  • All civil works
  • Design and installation of hard stand
  • Final certification, commissioning and compliance paperwork

Kokomo Resort

Petrolink Engineering was awarded the Contract to Design, Engineer, Supply and Install a new State of the Art system to provide fuel for the Six Star Kokomo Island Resort electricity generators as well as refuelling facilities. Petrolink supplied and installed both above and below ground environmentaly friendly fuel storage tanks and management system.

Robson Civil

Robson Civil commissioned Petrolink Engineering to install a new fuel facility of which to also utilise and incorporate existing fuel assets onsite. This installation included new components and the modification to an existing onsite Diesel storage tank. The project included construction of a new refuelling forecourt, suitable to service large trucks and light vehicles alike.

Pacific National

Petrolink Engineering was initially invited to be involved in a feasibility study and evaluation for the development of an on-site train refuelling facility for Pacific National at a coal collection point in the Hunter Valley coal fields region. Following this initial phase, the client was impressed with Petrolink’s professional approach and requested another three sites undergo feasibility studies.

Close Menu